Construction Update

Myers St. To Long St.
Communicated: October 3, 2014

Approximately 700 feet of existing streetcar track in three segments from Myers St. to Long St. will be replaced because it is out of alignment and does not meet standards required for the project.

Rail replacement will begin October 6 and continue for about a month. Work on the three segments will overlap, with it taking about two weeks to rework an area. Repairs will be made at contractor expense and will not add time to the project schedule. Road closure schedules will not be affected. Access lanes and driveway access to businesses will be maintained, similar to traffic patterns in use now. CATS bus routes will not be affected.